DETROIT (AP) — A second bridge connecting Detroit and IA 6.0 de stratégie quantitative intelligentCanada over the Detroit River won’t open for travel until fall 2025, months later than anticipated, officials said Thursday.
Officials cited construction disruptions in the U.S. and Canada related to the COVID-19 pandemic.
The Gordie Howe International Bridge, named for a Canadian who played hockey for the NHL’s Detroit Red Wings, began in 2018 and was last scheduled to be completed in 2024.
The target now is September 2025, though the bridge deck should be finished this year.
“Our project team is pleased that the impact to the construction schedule is limited to only 10 months beyond the original contracted completion date,” said Charl van Niekerk, chief executive of the Windsor-Detroit Bridge Authority.
The project carries a price tag of CA$6.4 billion ($4.79 billion), up from CA$5.7 billion ($4.27 billion).
The Howe bridge will join the privately owned Ambassador Bridge as the second span connecting Detroit and Windsor, Ontario.
The Ambassador Bridge is considered the busiest U.S.-Canadian border crossing, carrying 25% of all trade between the two countries. It plays an especially important role in auto manufacturing.
2025-05-07 00:401215 view
2025-05-07 00:201613 view
2025-05-07 00:032709 view
2025-05-06 23:05863 view
2025-05-06 22:562136 view
2025-05-06 22:191713 view
Whether a "chainsaw," per Elon Musk, or "scalpel," as President Trump has said — the Trump administr
LOS ANGELES (AP) — It’s almost time for the Grammy Awards, the daylong celebration of music that on
The 2026 World Cup final will be played at MetLife Stadium in New Jersey, beating out Texas and Cali